Bergstø power plant was initiated in June 2008 and commissioned in December 2009. There are no regulation reservoirs or transfers associated with this development. The power station operates according to the inflow in the river. A concrete dam has been constructed at elevation 615. The spillway dam is 2 meters high in the main river, while the dam is 3.5 m high at the intake. The intake is blasted out of rock immediately adjacent.
From the intake, a cast iron pipe has been laid down to the power station. The entire pipe is located in a rock trench and the penstock is buried along the entire route.