Småkraft AS was initially rejected for the project. This was largely because it was argued that the power plant would have a negative effect on ice formation downstream from where the station is located due to a higher temperature in the water passing through the power plant, and thus have a negative effect on the major ice climbing interests in the area. The case was passed on to the MPE, where it emerged that stopping production during the winter months as a mitigation measure for ice formation would be able to preserve the major ice climbing interests and thus the rejection was turned into a decision. The power plant now produces renewable electricity for the benefit of society and the environment, and stops production in the period between December 15 and March 31 for the benefit of the major ice climbing interests in the area.
The detailed plan was approved by NVE at the end of October 2017, allowing construction work to begin in November. The development went relatively smoothly after a good effort from the contractors and continued until the fall of 2018 when the generator ended up being delayed a few months. The project was then in danger of being delayed until May 2019, as it could be impossible to transport the generator up to the station if there was too much snow. Fortunately, the weather gods were on our side and the snow stayed away until the generator was in place and the project could go ahead.
The power plant has an inflow from a catchment area of 14.5 km2. The minimum water flow is 85 l/s in summer and 15 l/s in winter. The intake at elevation 927.5 and the station at elevation 660 give a head of 267.5 meters. Production is estimated at 6.08 GWh in a normal year. This corresponds to the electricity consumption of approximately 300 households.
The Pelton turbine has a maximum capacity of 1.22 m3/s and drives a 2845 kVA, 6600 V generator. The pipeline consists of both GRP and GJS and has a length of 1320 meters with a diameter of 600 mm. The voltage is transformed up to 22 kV before the power is delivered to the grid.