Skarelva power plant

The power plant utilizes the water flow from an 11.1 km2 field in Sør-Skjomen in Narvik municipality. The Vestskarelva and Snøskarelva rivers merge to form the Skarelva river and flow into the Storelva river. The Storelva river flows into Skjomenbotn in the very south of Sør-Skjomen.

The story

The farms Sandvoll and Skjomboten are the innermost farms in Skjomen in Narvik municipality. Together they have large outlying areas, with associated rivers. Much of the power resources in Skjomen were developed in the early 1970s, but the Vestskarelva and Snøskarelva rivers were not affected by the development at the time.

The landowners were aware that the river could have good potential for a small power plant. How the value creation from the river was to be realized was the subject of a fairly vigorous reality check, where it was decided that a professional developer should be brought in as a partner.

In 2004, a contract was signed with Småkraft, which assumed the risk, the work on the licensing process and the actual development. NVE granted a license in 2008. This was appealed by Narvik municipality. The appeal was rejected by the MPE in December 2009. The excavators arrived in the summer of 2011. And by the end of 2012, the power plant was ready to make its contribution in the form of new renewable energy and local business income.

With natural stone walls and a glass facade, the station building is beautiful to look at, where it is nicely adapted to the terrain close to the river.

The project

The implementation of the project has had its challenges along the way, such as appealing to the Ministry of Petroleum and Energy for a license, a pipeline mostly in a mountain trench, difficult and costly access to the power grid and telecommunications network, and a harsh winter during the construction phase – to name but a few.
The collaboration with the landowners has been active and good. Their contribution in the form of local knowledge and presence during the construction phase has contributed to good project implementation.

All suppliers have delivered as expected. As a result, the construction has been able to keep to the schedule. This is not a matter of course in this type of project.

Skarelva power plant has inflow from two rivers, Snøskarelva and Vestskarelva, with a total catchment area of 11.1 km2. The minimum flow is 20 l/s in winter for both intakes, while it is 300 l/s for Snøskarelva and 20 l/s for Vesterskarelva in summer. Intakes in both rivers at elevation 455 and the power station at elevation 18 give a head of 437 meters. Production is estimated at 11.9 GWh in a normal year. This corresponds to the electricity consumption of 595 households.

The Pelton turbine has 4 jets with a maximum capacity of 1.35 m3/sec and drives a generator of 5500 kVA, 6600 v. All power is transformed up to 22 kV and delivered to the grid.

The intake dams are built as blasted culverts with low dams in reinforced concrete with a prefabricated intake structure. The intakes are well adapted to the terrain at the site, and appear as a very modest intervention. The pipeline is in PE pipe for each branch and in cast iron from the branch to the station. The diameter of the PE is 0.6m and of the cast iron 0.7m. The entire waterway is buried.

The power station building is constructed in the well-known Småkraft style, covers 80 m2, is built above ground, and is well integrated into the terrain. The wastewater is piped into the river.

Technical data

Rainfall field

11,1 km²

Minimum water flow

Summer: 300 l/s
Winter: 20 l/s

Intake elevation

455,0 m

Power station elevation

18,0 m

Drop height

437,0 m

Production

12,0 GWh
This corresponds to electricity for 750 households.